Reset
Images
WSS between ch 96+700 to ch 97+200
Images
WSS between ch 86+500 to ch 87+00
Images
WSS between ch 84+400 to 81+800
Images
WSS between ch 84+00 to ch 84+400
Images
Kundevahal Tunnel South Portal Rob erection in progress
Images
Work yet to start from Ch19520 to 19700
Images
Work yet to start from Ch19+520 to 19+700
Images
Shotcrete at Kundevahal Tunnel South Portal
Images
Ribs erection for Heading at Kundevahal Tunnel South Portal started on today
Images
NH4B -ROB road open for traffic of phase -1 JNPT end
Images
MNRUB-104A slab curing wip
Images
MNRUB-104A curing wip
Images
MNRUB -49 not yet started
Images
Mnb 168 work stand still
Images
MNB -43 not yet started
Images
MNB -23 precast box erection completed
Images
Gawan phata ROB -work stand still
Images
PSC Solid slab PS-17433A
Images
177 MJB end span
Images
Vahale dhumale ROB approach road A2 Side
Images
Vahale dhumale ROB – bow string girder assembly and trussel erection in progress
Images
ROB -KD2 completed miscellaneous work is balance
Images
psc slab PS118 169 c&dmjb
Images
No work
Images
MJRUB -67 work stand still
Images
MJB-177 Precast solid slab
Images
MJB -68E work in progress
Images
Kharbao Yard Blanket work in progress.
Images
Kharbao Viaduct – A1 side – Span P28 – 29
Images
Hill cutting work between ch 56+900 to ch 57+120
Images
Hill cutting work at ch88+540 to ch 88+600
Images
Ev2 for Blanket material at ch 86+100
Images
ch. 84+100 to ch 84+450 WSS
Images
ch 96+700 to ch 97+200 WSS
Images
01 Up Co. – WSS
Images
Viaduct-163D P30(LHS) pier shaft 1st lift concrete pouring started
Images
Viaduct-163D P12 raft concrete pouring started
Images
ROB BHIWANDI – WIP
Images
PSC Solid slab PS-216342B concreting done 300322.
Images
MNRUB 121 – YTS (2)
Images
MNB 121A – WSS (2)
Images
CTP-11 Kharbao Viaduct
Images
MJRUB 127 -YTS
Images
MJB 151 WSS
Images
MJB 146 & 147B A2 Pedestal concrete pouring started
Images
MJB 142 WSS
Images
MJB 139 – – WIP (Work resumed
Images
MJB 138 – Main Track – WSs
Images
MJB 137 – WSS since 28-May
Images
MJB 136 – WSS
Images
MJB 134 – WSS
Images
MJB 125B – WSS – View from ROW
Images
MJB 119A A2 abutment
Images
MJB -68E psc I girder -05 casting completed during night shif
Images
MJB 2 Up Co. Construction WSS – View from JNPT End
Images
Kopar Viaduct – WIP
Images
Kopar Viaduct WIP
Images
Kharbao Viaduct -RFO Span (P37 P38)
Images
Kharbao Viaduct WIP (P35 to A1. Deck slab in progress at P35-34 Span)
Images
Kharbao RFO – P37-38 WIP
Images
CTP-11 MJB 138
Images
Ch76+700 to ch 67+340 WSS
Images
Ch 70+700 to ch 71+100 WSS
Images
Ch 65+250 to ch 65+700 WSS
Images
Ch 59+100 to ch 59+550 WSS
Images
Ch 58+650 to ch 59+030 YTS
Images
Ch 57+500 to ch 58+650 WSS
Images
ch 15+760 to 15+770 LHS side
Images
Bhiwandi ROB Pipeline – U Trough construction completed _View from VAITARNA End
Images
142B not yet started
Images
119B – YTS_View from ROW
Images
Viaduct-163D P23
Images
Viaduct-163D P12 raft
Images
Viaduct 172 wip
Images
South tunnel south portal , WSS portal work
Images
South tunnel , wip
Images
Rob2 vs2, wip
Images
P31A Pilecap reinforcement fixing work in progress Kalamboli RFO A1 side.
Images
North tunnel south portal, collapse section wip
Images
North tunnel , lining work in progress
Images
North deep cut work stand still
Images
Mnrub 171
Images
MNRUB -68F box 1span wearing coat casting completed
Images
Mnb 170c wss
Images
Mnb 170b work stand still
Images
Mnb 170a work stand still
Images
Mnb 170 work stand still
Images
Mnb 169 , WSS
Images
Mnb 168, WSS
Images
MNB -23 precast box erection in progress
Images
MNB – 26
Images
Mjb 178 wip
Images
Mjb 177 work stand still
Images
Mjb 169c&d, slab launching wip
Images
Mjb 169A , work stand still
Images
Kundevahal Tunnel South Portal excavation
Images
Kundevahal Tunnel North Portal face preparation is standstill
Images
Isolated tunnel , WSS
Images
Isolated deep cut, wip
Images
Ch95+835 to 95+840 (RHS)
Images
Ch 91+025 to ch 91+330 YTS
Images
Ch 86+550 to ch 87+110 WSS
Images
Central deep cut, WSS
Images
Casting yard, virar, wip
Images
177 mjb
Images
Solid slab PS1 Errection Started at MJB 169C&D(P2P3)
Images
PSC Solid slab PS-173 33A concreting done 299322.
Images
NH4B – ROB 2 nd layer DBM in progress of 12.5 m carriageway
Images
MNB -42C box wall JNPT
Images
Kalamboli RFO Pile cap P-31A rf placing start.
Images
Girder errection 4350217224
Images
Ch 29+566 to 29+580
Images
NH4B – ROB 2 nd layer DBM in progress of 12.5 m carriageway
Images
Viaduct-163D P30 (RHS) 1st lift concrete pouring started
Images
PSC Solid slab PS-216242B concreting done 298322.
Images
NH4B -ROB laying of DBM 1st layer in progress of 12.5m carriageway
Images
NH4B -ROB 1st layer of DBM complete 2nd layer in progress of 12.5 m carriageway
Images
MNB – 21
Images
Viaduct-163D P30 (RHS) 1st lift concrete pouring started
Images
ROB 142B not yet started
Images
PSC Solid slab PS-216242B concreting done 298322.
Images
North deep cup work stand still
Images
NH4B -ROB laying of DBM 1st layer in progress of 12.5m carriageway
Images
NH4B -ROB 1st layer of DBM complete 2nd layer in progress of 12.5 m carriageway
Images
NH4B-ROB.
Images
NH4B -ROB laying of BC in progress of 7.6 m carriageway
Images
MNB -21 U trough raft casting completed
Images
MNB -15 U-type Rwall 1st lift casting completed
Images
WSS between ch 84+00 to 84+450
Images
WSS between ch 61+700 to ch 61+900
Images
WSS between ch 57+600 to ch 57+780
Images
MNRUB 121 – YTS
Images
MNRUB 119B – YTS – View from ROW
Images
MNB 121D – YTS
Images
MNB 121C – YTS (Construction work to commence.)
Images
MNB 121A – WSS
Images
Kopar Viaduct View from A1 Side
Images
Kopar Viaduct P12-13 Span – WIP – I Girder De-shuttering in progress.
Images
WSS between ch 84+00 to 84+450
Images
WSS between ch 61+700 to ch 61+900
Images
Viaduct-163D P23(LHS)
Images
NH4B-ROB
Images
NH4B -ROB DBM
Images
NH4B -ROB (2)
Images
MRUB-121
Images
MRUB-119B
Images
MNRUB 121 – YTS
Images
MNRUB 119B – YTS – View from ROW
Images
MNB-121D
Images
MNB-121C
Images
MNB-121A
Images
MNB 121D – YTS
Images
MNB 121C – YTS (Construction work to commence.)
Images
MNB 121A – WSS
Images
WSS between ch 86+500 to ch87+00
Images
WSS between ch 81+600 to ch 82+00
Images
WSS between ch 77+800 to ch 78+200
Images
WSS between ch 58+100 to 59+000
Images
WSS between ch 66+600 to ch 67+300
Images
WSS between ch 86+500 to ch87+00
Images
WSS between ch 81+600 to ch 82+00
Images
WSS between ch 77+800 to ch 78+200
Images
WSS between ch 58+100 to 59+000
Images
WSS between ch 57+600 to ch 57+780
Images
WSS between ch 66+600 to ch 67+300
Images
Virar casting yard
Images
Viaduct 172 wip
Images
South tuunel north approach mobile crusher working
Images
South tunnel wip
Images
Rob2 vs2 wip
Images
ROB DT-1
Images
ROB BHIWANDI – WIP (Work resumed
Images
psc slab PS24 169
Images
North tunnel south portal collapse section
Images
North tunnel lining wip
Images
NH4B -ROB -crash barrier 2nd lift casting completed at D point side 12.8 m carriageway
Images
Mnrub 169b
Images
Mnb 170c
Images
Mnb 170a wss
Images
Mnb 170 wss
Images
Mnb 169 wss
Images
Mnb 168
Images
MNB -58 top layer backfilling completed
Images
MNB -23 curing in progress
Images
MJRUB 127 – YTS_ View from ROW
Images
MJRUB -67 work stand still
Images
MJB-119A
Images
MJB-106
Images
NH4B -work in progress
Images
NH4B -ROB layer of WMM in progress of 7.6 m carriageway
Images
NH4B -ROB
Images
MNB 23
Images
MNB – 15
Images
PSC Solid slab PS-37333A
Images
MJB 147 – Work stand still
Images
MNB -63 toe wall casting completed
Images
MNB -58 Toe wall casting completed
Images
MJRUB127-CH.59+407.50-YTS
Images
Kundevahal Tunnel North portal work not yet taken up
Images
Kharbao Viaduct I Girder Erection A1 Side Agency Ms Tukaram Cranes- (7)
Images
MNB126A-CH.56+832-WIP
Images
MNB125-CH.56+682-WSS since 06-03-24
Images
MNB125A-CH.55+955-WIP
Images
MNB124-CH.55+317-YTS
Images
MNB124A-CH.55+134-YTS
Images
MNB123A-CH.54+675-WIP
Images
MJRUB 127 – YTS – View from A2-ROW Corner
Images
MJB139-CH.69+396-View from JNPT End-WIP
Images
MJB138-CH.68+447.94-View from IR Side & Vaitarna End-WSS since 13-06-2023 (PSC Solid slab to be commen
Images
MJB-136-CH.65+776.31-(A2)WSS since 29.11.23 (Girders stressing,grouting & launching to be commenced)
Images
MJB134-CH.63+721-(A2)View from Vaitarna side & ROW corner-WSS since 01.02.24 (Girders stressing,grouti
Images
MJB125B-CH.56+152-WSS Since 02.02.24(PSC solid slab yet to be commenced)
Images
MJB 138 – Main Track – WSS; Up Track – WIP – Shoring arrangement completed. Pile chipping in progress at A1; – View from Vaitarna End
Images
MJB 136 – WSS – View from ROW
Images
MJB 134 – WSS _ View from Vaitarna End-Row Corner
Images
MJB 134 – WSS _ View from JNPT End-Row Corner
Images
MJB 125B – WSS – View from ROW
Images
MJB 2 Up Co. Construction WSS – View from JNPT-IR Corner
Images
1UPCO-CH.69+005-WIP
Images
Kharbao Viaduct I Girder Erection A1 Side Agency Ms Tukaram Cranes- (5)
Images
MNB -62 floor apron cement grout completed
Images
MNB -33A Abutment A1 final lift concreting in progress
Images
MNB -32 excavation work in progress
Images
MNB -05 IR existing bridge dismantling in progress
Images
Kharbao Viaduct I Girder Erection A1 Side Agency Ms Tukaram Cranes- (4)
Images
Kharbao Viaduct I Girder Erection A1 Side Agency Ms Tukaram Cranes- (3)
Images
Kharbao Viaduct I Girder Erection A1 Side Agency Ms Tukaram Cranes
Images
JNPT ASS building- GF slab concrete started
Images
Kharbao Viaduct I Girder Erection A1 Side Agency Ms Tukaram Cranes-
Images
Kharbao Viaduct I Girder Erection A1 Side Agency Ms Tukaram Cranes- (2)
Images
MNRUB-119C Raft Foundation 66200 cum concrete pouring wip.
Images
MNB140A-CH.70+495-WSS
Images
MNB125C-CH.56+321-WIP
Images
Kopar Viaduct-P13-P15-Ch.51+047-WSS
Images
kopar Viaduct -P17-A2-Ch.51+047-WIP
Images
Kopar Viaduct -P15-P16-Ch 51+047-WIP
Images
Kopar Viaduct -P12-P13-Ch.51+047-WIP
Images
Kopar Viaduct -P11-P12-Ch 51+047-WSS
Images
Kopar Viaduct -P10-P11-Ch.51+047-WSS
Images
Kopar Viaduct -P9-P10-Ch.51+047-WSS
Images
Kopar Viaduct -P8-P9-Ch.51+047-WSS
Images
Kopar Viaduct -P7-P8-Ch.51+047-WSS
Images
Kopar Viaduct -P6-P7-Ch.51+047-WSS
Images
Kopar Viaduct -P3-P6-Ch.51+047-WSS
Images
Kopar Viaduct -P2-Ch.51+047-WSS
Images
Kopar Viaduct -A2-Ch.51+047-WIP
Images
Kopar Viaduct -A1-P1-Ch.51+047-WSS
Images
Rwall final lift casting completed at ch 8+300 to 8+320 RHS side
Images
Ghawan phata hill cuttingIR permit block from 1730 to 1900cutting work in progress
Images
Concrete pouring started of Return Wall and abutment wall 1st lift at MJB-145 A1 side ch 77+364
Images
MNB125C-CH.56+321-WIP
Images
P-28 viaduct 172 reinforcement placing of pile cap wip
Images
MNRUB133E-CH.63+477-YTS
Images
MNRUB132-CH.61+878-YTS
Images
MNRUB128B-CH.59+607-YTS
Images
MNB137D-CH.67+244-WSS
Images
MNB137C-CH.66+870-YTS
Images
MNB137B-CH.66+612-WSS Since 24.02.24
Images
MNB137A-CH.66+410-WSS
Images
MNB134A-CH.64+162-WIP
Images
MNB133D-CH.62+607-WSS
Images
MNB133C-CH.62+507-WSS
Images
MNB133B-CH.62+348-YTS
Images
MNB133A-CH.62+097-YTS
Images
MNB133A-CH. 63+289-YTS
Images
MNB132B-CH.61+971-WSS since 15-Feb-24
Images
MNB132A-CH.61+594-YTS
Images
MNB131-CH.61+202-WIP
Images
MNB130-CH.61+037-YTS
Images
MNB130A-CH.60+982-YTS
Images
MNB129-CH.60+523-WSS
Images
MNB128-CH.60+222-WIP
Images
MNB128C-CH.59+461-YTS
Images
MNB -13A box wall & top slab concreting in progress
Images
MJB137-CH.67+951.49-(A2)WIP
Images
Kundevahal Tunnel South Portal pipe roofing in progress
Images
Kharvao Viaduct(A1)-CH.1+622-WIP
Images
Ghawan phata hill cuttingIR permit block from 1940 to 2110cutting work in progress
Images
Vahale dhumale ROB – 4 member of bottom cord cleaning and zinc cromate paint completed and thickeness checked
Images
South Tunnel No work
Images
ROB DT-1
Images
North Tunnel No work
Images
MNB142B – work not started
Images
MNB140-CH.70+304-YTS
Images
MNB127D-CH.59+129-WSS from 06-Mar-24.
Images
MNB127C-CH.58+926-YTS (No further progress till date)
Images
MNB127B-CH.58+306-WSS Since 15-02-24
Images
MNB127A-CH.58+088-WSS from 12-Feb-24.
Images
MNB126B-CH.57+246-WSS (No further progress till date)
Images
MNB126A-CH.56+832-WIP
Images
MJB 147 – work stand still
Images
MJB 142 – Work Stand Still
Images
MJB 136 – WSS – View from ROW- ROW Corner
Images
MJB -66 parapet wall concreting in progress of span A1-P1 DL
Images
Isolated Tunnel No work
Images
Gawan phata water pipe line A1 foundation reinforcement in progress
Images
Gawan phata IR block permit 1800 to 1920 cutting in progress
Images
ch 91+025 to ch 91+720 work not yet started
Images
Concrete pouring started of Girder IG-17 (2.4m height) at Viaduct 159.
Images
Work yet to start from Ch19+520 to 19+700
Images
Viaduct- 163D P13 pier shaft 1st lift pouring start
Images
ROB BHIWANDI – WSS – View from JNPT End
Images
RFO-Kharbao-View from JNPT End- P38-WSS Since 21-02-24
Images
RFO-Kharbao- View from Vaitarna End-P37-WIP
Images
MNRUB123-CH.54+787-YTS
Images
MNB125D-CH.56+467-Completed
Images
MNB125-CH.56+682-WIP
Images
MNB124-CH.55+317-YTS
Images
MNB124A-CH.55+134-YTS
Images
MNB123A-CH.54+675-WIP
Images
MJRUB127-CH.59+407.50-YTS
Images
MJRUB 127 – YTS – View from A2-ROW Corner
Images
MJB139-CH.69+396-View from JNPT End-WIP
Images
MJB138-CH.68+447.94-View from IR Side & Vaitarna End-WSS since 13-06-2023 (PSC Solid slab to be commen
Images
MJB134-CH.63+721-S(A1)WSS since 01.02.24 (Girders stressing,grouting & launching to be commenced)
Images
MJB134-CH.63+721-(A2)View from Vaitarna side & ROW corner-WSS since 01.02.24 (Girders stressing,grouti
Images
MJB125B-CH.56+152-WSS Since 02.02.24(PSC solid slab yet to be commenced)
Images
MJB 138 – Main Track – WSS; Up Track – WIP – Shoring arrangement completed.; – View from JNPT End
Images
MJB 134 – WSS _ View from Vaitarna End-Row Corner
Images
MJB 134 – WSS _ View from JNPT End-Row Corner
Images
MJB 125B – WSS – View from ROW
Images
MJB 2 Up Co. Construction WSS – View from JNPT End
Images
Kundevahal Tunnel South Portal face preparation in progress drilling for pipe roofing in progress
Images
Kundevahal Tunnel North portal work not yet taken up
Images
Gavan phataIR permit block from 18.10 to 19.45Cutting work in progress at ch11+130
Images
ch 84+200 to ch 85+00 WSS
Images
ch 66+600 to 67+300 WSS
Images
Ch 58+600 to ch 59+300 work not yet started
Images
Bhiwandi ROB-CH.56+215.539- View from JNPT End-WSS since 06.01.24
Images
Bhiwandi Pipeline-CH.56+293-Completed
Images
2UPCO-CH.69+396-View from JNPT End-WSS since 31-03-2023
Images
1UPCO-CH.69+005-WIP
Images
1UPCO-CH.69+005-WIP(1)
Images
MNB125D-CH.56+467-Completed
Images
MNB125-CH.56+682-WIP
Images
Viaduct 159 P3
Images
P2605 cage lowering in progress at viaduct 172
Images
JasaiWSS From Ch6+300 to 7+440
Images
Gavan phataIR permit block from 18.55 to 20.00Cutting work in progress at ch11+200
Images
Drilling for pipe roofing in progress at Kundevahal Tunnel South Portal
Images
CTP-11 Kharbao Viaduct I Girder Erection A1 Side Agency Ms Tukaram Crane
Images
CTP-11 Kharbao Viaduct I Girder Erectio
Images
Routine Vertical Load test setup at P2710 at viaduct -172
Images
MNB135A-CH.65+154-WSS
Images
MNB134B-CH.64+318-WSS
Images
MNB133-CH.63+289-YTS
Images
RFO-Kharbao-View from JNPT End- P38-WSS Since 21-02-24
Images
RFO-Kharbao- View from Vaitarna End-P37-WIP
Images
MNRUB128B-CH.59+607-YTS
Images
MNB140-CH.70+304-YTS
Images
MNB140A-CH.70+495-WSS
Images
MNB137D-CH.67+244-WSS
Images
MNB137C-CH.66+870-YTS
Images
MNB137B-CH.66+612-WSS Since 24.02.24
Images
MNB137A-CH.66+410-WSS
Images
MNB136A-CH.66+021.-WSS
Images
MNB130A-CH.60+982-YTS
Images
MNB129-CH.60+523-WSS
Images
MNB128-CH.60+222-WIP
Images
MNB128C-CH.59+461-YTS
Images
MNB128A-CH.59+461-YTS
Images
MNB127D-CH.59+129-WIP
Images
MNB127C-CH.58+926-YTS (No further progress till date)
Images
MNB127B-CH.58+306-WSS Since 15-02-24
Images
MNB127A-CH.58+088-WIP
Images
MNB126B-CH.57+246-WSS (No further progress till date)
Images
MNB126A-CH.56+832-WSS (No further progress till date)
Images
MNB125D-CH.56+467-WIP
Images
MNB125-CH.56+682-WSS since 06-03-24
Images
MNB125C-CH.56+321-WIP
Images
MNB-121D Ch.53+014
Images
MNB-121C Ch.52+905
Images
MNB-121B Ch.52+708
Images
MNB-121A Ch.52+148
Images
MJB139-CH.69+396-View from JNPT End-WIP
Images
MJB138-CH.68+447.94-View from JNPT End-WSS since 13-06-2023 (PSC Solid slab to be commenced & upconnec
Images
MJB138-CH.68+447.94-View from IR Side & Vaitarna End-WSS since 13-06-2023 (PSC Solid slab to be commen
Images
MJB137-CH.67+951.49-(A2)WIP
Images
MJB137-CH.67+951.49-(A1)
Images
MJB-136-CH.65+776.31-WSS since 29.11.23 (View from ROW)
Images
MJB-136-CH.65+776.31-(A1)WSS sice 29.11.23 (Girders stressing,grouting & launching to be commenced)
Images
Minor RUB-121E Ch.53.280
Images
Minor RUB-121 Ch.51+654
Images
Kopar Viaduct -P17-P14-Ch.51+047
Images
Kopar Viaduct -P17-A2-Ch.51+047
Images
Kopar Viaduct -P14-P13-Ch.51+047
Images
Kopar Viaduct -P13-P12-Ch.51+047
Images
Kopar Viaduct -P12-P11-Ch.51+047
Images
Kopar Viaduct -P11-P09-Ch.51+047
Images
Kopar Viaduct -P9-P7-Ch.51+047
Images
Kopar Viaduct -P7-P4-Ch.51+047
Images
Kopar Viaduct -P3-P2-Ch.51+047
Images
Kopar Viaduct -A1-P2-Ch.51+047
Images
Kharvao Viaduct-View from P24 JNPT End
Images
Kharvao Viaduct(A1)-CH.1+622-WIP
Images
Kharvao Viaduct P55 View from Vaitarna End
Images
2UPCO-CH.69+396-View from JNPT End-WSS since 31-03-2023
Images
1UPCO-CH.69+005-WIP
Images
MNB136A-CH.66+021.-WSS
Images
MNB128A-CH.59+461-YTS
Images
MNB127D-CH.59+129-WIP
Images
MNB127A-CH.58+088-WIP
Images
MNB126A-CH.56+832-WSS (No further progress till date)
Images
MNB125D-CH.56+467-WIP
Images
MNB125-CH.56+682-WSS since 06-03-24
Images
MJB138-CH.68+447.94-View from JNPT End-WSS since 13-06-2023 (PSC Solid slab to be commenced & upconnec
Images
MNB126A-CH.56+832-WSS (No further progress till date)
Images
MNB125D-CH.56+467-WIP
Images
ROB DT-1 No work
Images
NP4 pipe erection in progress at MNB-146A
Images
MNB—116 Box errection wip 99108 no’s.
Images
MNB -06 IR existing bridge dismantling completed
Images
MNB -04 IR existing bridge dismantling completed
Images
MJB-114 P-1 piercap wip
Images
MJB-106 ballast retainer wip
Images
MJB 142 work stand still
Images
Kalamboli RFO P-35 Pier cap Rf wip
Images
Kalamboli RFO P-34 pile cap Rf wip
Images
Cross hole test conducted at viaduct 172
Images
Concrete pouring started for IG 08 of MJRUB 146&147B at Nagle PC yard
Images
142B work not yet started
Images
MNRUB133E-CH.63+477-YTS
Images
MNRUB132-CH.61+878-YTS
Images
MNRUB123-CH.54+787-YTS
Images
MNB132B-CH.61+971-WSS since 15-Feb-24
Images
MNB125A-CH.55+955-WSS Since 14-02-24
Images
MNB124-CH.55+317-YTS
Images
MNB124A-CH.55+134-YTS
Images
MNB123A-CH.54+675-WIP
Images
MJB134-CH.63+721-S(A1)WSS since 01.02.24 (Girders stressing,grouting & launching to be commenced)
Images
Work yet to start from Ch52+700 to 53+500
Images
MNB125A-CH.55+955-WSS Since 14-02-24
Images
MNB125A-CH.55+955-WSS Since 14-02-24
Images
MNB -06 IR existing bridge dismantling in progress
Images
Gavan phataIR permit block duration from 18.55 to 20.10Cutting work in progress at ch 11+200
Images
Kundevahal Tunnel South Portal face preparation in progress (2)
Images
WSS Formation work from Ch19+460 to 19+520
Images
Work yet to start from Ch19+520 to 19+700
Images
South Tunnel No work
Images
ROB BHIWANDI – WSS – View from Vaitarna End
Images
ROB BHIWANDI – WSS – View from JNPT End
Images
North Tunnel No lining work due to non availability of waterproofing membrane at site
Images
MJRUB 127 – YTS – View from A1-ROW Corner
Images
MJB 139 – Construction WSS – View from JNPT-IR Corner
Images
MJB 136 – WSS – View from ROW- ROW Corner
Images
MJB 134 – WSS _ View from JNPT End-Row Corner
Images
MJB 125B – WSS – View from ROW
Images
MJB 2 Up Co. Construction WSS – View from JNPT End
Images
Isolated tunnel No work since 16th jan 2024
Images
Gawan phata ROB -work stand still
Images
WSS ch 66+600 to ch 67+300
Images
WSS ch 65+400 to ch 66+200
Images
work not yet started ch 91+025 to ch 91+750
Images
Work not yet started ch 58+600 to 59+200
Images
Kundevahal Tunnel South Portal face preparation in progress
Images
Kundevahal Tunnel South Portal face preparation in progress
Images
MJB125B-CH.56+152-WSS Since 02.02.24(PSC solid slab yet to be commenced)
Images
Bhiwandi ROB-CH.56+215.539- View from JNPT End-WSS since 06.01.24
Images
Bhiwandi Pipeline-CH.56+293-Completed
Images
JasaiWSS From Ch6+300 to 7+440
Images
Kundevahal Tunnel South Portal face preparation in progress1
Images
WSS Formation work from Ch19+460 to 19+520
Images
Work yet to start from Ch19+520 to 19+700
Images
MJRUB -67 A2 side
Images
MJB 169A work stand still.
Images
MJB 147 work stand still
Images
MJB 142 Bridge – Work stand still
Images
JasaiWSS From Ch6+300 to 7+440
Images
Gawan phata ROB -work stand still
Images
Animal overpass 142B not yet started
Images
Kundevahal Tunnel South Portal face preparation in progress2
Images
MJB 139 – Construction WSS – View from JNPT End.
Images
01 Up Co. – WSS since 13-Feb-2024_ View from Vaitarna End
Images
Kundevahal Tunnel South Portal face preparation in progress3
Images
ROB BHIWANDI – WSS – View from JNPT
Images
North deep cut No work
Images
MNRUB-104A raft bottom level excavation done
Images
MNB -65 counter fort Return wall completed
Images
MJRUB 127 – YTS – View from ROW
Images
MJB-119A A1 abutment wip
Images
MJB-114 A1 abutments pier cap wip
Images
MJB-106 ballast retainer wip
Images
MJB-88 A1 abutments and ballast retainer wip
Images
MJB-83 ballast retainer and wearing coat wip
Images
MJB 138 – Main Track – WSS; Up Track – Shoring arrangement in progress; – View from JNPT End
Images
MJB 136 – WSS – View from ROW
Images
MJB 134 – WSS – View from Vaitarna End- ROW Corner
Images
MJB 125B – WSS – View from ROW
Images
MJB 2 Up Co. – Construction WSS – View from JNPT End
Images
Kalamboli viaduct P-20 piercap casting wip
Images
Isolated tunnel No work
Images
Collapsed slopes No work
Images
Central deep cut No work
Images
Kundevahal Tunnel South Portal face preparation in progress4
Images
KoparWork yet to start from DFCC Ch51+400 to 51+660
Images
WSSFrom Ch19+460 to 19+520
Images
Work yet to start from DFCC Ch19+520 to 19+700
Images
Panvel StationReliance Diesel pipe diverted from MNB-68G Near@ch23+650Connectivity done -pipe line issue closed
Images
MNB125A-CH.55+955-WIP
Images
MNB125A-CH.55+955-WIP
Images
MNB137B-CH.66+612-WIP
Images
MNB125-CH.56+682-WSS since 31-01-24 (No further progress till date)
Images
MNB137B-CH.66+612-WIP
Images
MNB125-CH.56+682-WSS since 31-01-24 (No further progress till date)
Images
MNB125-CH.56+682-WSS since 31-01-24 (No further progress till date)
Images
MJB 142 work stand still
Images
MJB 147 work stand still
Images
142B
Images
ROB BHIWANDI – WSS – View from JNPT End
Images
Isolated Tunnel No work
Images
Kundevahal South Tunnel
Images
MJB-114 pier work in progress
Images
MJB-119A work in progress
Images
MJRUB -67
Images
MNB127D-CH.59+129-WSS (No further progress till date)
Images
MNB127B-CH.58+306-WIP
Images
MNB127A-CH.58+088-WIP
Images
MNB126B-CH.57+246-WSS (No further progress till date)
Images
MNB126A-CH.56+832-WSS (No further progress till date)
Images
MNB125D-CH.56+467-WIP
Images
MNB125-CH.56+682-WSS (No further progress till date)
Images
MNB125A-CH.55+955-WIP
Images
RFO-Kharbao-View from JNPT End- P38-WIP
Images
Bhiwandi ROB-CH.56+215.539- View from JNPT End-WSS since 06.01.24
Images
Bhiwandi Pipeline-CH.56+293-Completed
Images
Gawan phata ROB
Images
Kharvao Viaduct(A1)-CH.1+622-WIP
Images
Kharvao Viaduct-CH.68+885-WIP
Images
MNB129-CH.60+523-WSS
Images
MNB128-CH.60+222-WIP
Images
MNB125C-CH.56+321-WIP
Images
MNB124-CH.55+317-YTS
Images
MNB124A-CH.55+134-YTS
Images
MNB123A-CH.54+675-WIP
Images
MNRUB123-CH.54+787-YTS
Images
Kharbao Keymen and type 2 quarters- Work not started
Images
MJB-136-CH.65+776.31-(A1)WSS sice 29.11.23 (Girders stressing,grouting & launching to be commenced)
Images
MJB-136-CH.65+776.31-(A2)WSS since 29.11.23 (Girders stressing,grouting & launching to be commenced)
Images
MJB-136-CH.65+776.31-WSS since 29.11.23 (View from ROW)
Images
2UPCO-CH.69+396-View from JNPT End-WSS since 31-03-2023
Images
MJB-119A abutment A2 excavation wip
Images
MJB137-CH.67+951.49-(A1)
Images
MJB137-CH.67+951.49-(A2)WIP
Images
MJB138~1
Images
MJB139-CH.69+396-View from JNPT End-WSS since 30.03.23
Images
MJRUB127-CH.59+407.50-YTS(1)
Images
Kharvao Viaduct P55 View from Vaitarna End
Images
MNB137D-CH.67+244-WSS
Images
MNB137C-CH.66+870-YTS
Images
MNB137B-CH.66+612-WIP
Images
MNB137A-CH.66+410-WSS
Images
MNB136A-CH.66+021.-WSS
Images
MNB134B-CH.64+318-WSS
Images
MNB134A-CH.64+162-WIP
Images
MNB133D-CH.62+607-WSS
Images
MNB133C-CH.62+507-WSS
Images
MNB133B-CH.62+348-YTS
Images
MNB133A-CH.62+097-YTS
Images
MNB132C-CH.61+929-YTS
Images
MNB132B-CH.61+971-WSS
Images
MNB132A-CH.61+594-YTS
Images
MNB131-CH.61+202-YTS
Images
MNB130-CH.61+037-YTS
Images
MNB130A-CH.60+982-YTS
Images
MNB128C-CH.59+461-YTS
Images
MNB128A-CH.59+461-YTS
Images
MNRUB133E-CH.63+477-YTS
Images
MNRUB132-CH.61+878-YTS
Images
MNRUB128B-CH.59+607-YTS
Images
Kundevahal Tunnel South Portal face preparation in progress5
Images
MNB132C-CH.61+929-YTS
Images
MJB-106 Ballast retainer wip
Images
MJB-114 abutment A1 shutter wip
Images
1st stage stressing start of IG-08 at mjb-142
Images
GAVANP~1
Images
P2605 pile cage lowering in progress at Viaduct 172
Images
MNB140-CH.70+304-YTS
Images
MNB140A-CH.70+495-WSS
Images
MNRUB-106A U trough Rock breaking wip
Images
MNRUB-106A U trough Rock breaking wip
Images
Kundevahal South Tunnel 01
Images
Second layer of wire mesh completed at Kundevahal Tunnel South Portal
Images
2nd stage stressing start of IG-04 at mjb-142
Images
Plate load test started at Viaduct-163D, P15 foundation
Images
MJB-136-CH.65+776.31-(A1)WSS sice 29.11.23 (Girders stressing,grouting & launching to be commenced)
Images
MJB-136-CH.65+776.31-(A2)WSS since 29.11.23 (Girders stressing,grouting & launching to be commenced)
Images
MJB-136-CH.65+776.31-WSS since 29.11.23 (View from ROW)
Images
2UPCO-CH.69+396-View from JNPT End-WSS since 31-03-2023
Images
MJB-119A Abutment A1 pier casting wip
Images
MJB125B-CH.56+152-WSS Since 02.02.24(PSC solid slab yet to be commenced)
Images
MJB134~1
Images
MJB134-CH.63+721-S(A1)WSS since 01.02.24 (Girders stressing,grouting & launching to be commenced)
Images
MJB138~1
Images
MJB139-CH.69+396-WSS since 30.03.23
Images
Bhiwandi ROB-CH.56+215.539- View from JNPT End-WSS since 06.01.24
Images
IG-41 Girder concrete started at viaduct 152 & 153
Images
Second layer wire mesh fixing in progress at Kundevahal Tunnel South Portal
Images
Kharbao Viaduct – A1 Side – Span A1-P1 – I-Girder No. 03 – 1.7m
Images
Kharbao Viaduct – RFO Span (P37-P38) – (1.8m dia. Pile)
Images
MJB-114 P1 pier shutter wip 1st lift
Images
MJB-119A abutments A1 (6th lift ) shutter wip
Images
P37-CH.1+622-WIP
Images
Span P15-P16-Ch.51.047-51+247-WIP
Images
Span P16-P17-Ch.51+047-51+247-WIP
Images
MNB136A-CH.66+021.-WSS
Images
MNB135A-CH.65+154-WSS
Images
MNB133A-CH.62+097-YTS
Images
MNB132C-CH.61+929-YTS
Images
MNB131-CH.61+202-YTS
Images
MNB130-CH.61+037-YTS
Images
MNB130A-CH.60+982-YTS
Images
MNB128A-CH.59+461-YTS
Images
MNB125C-CH.56+321-WIP
Images
MNRUB133E-CH.63+477-YTS
Images
MNRUB132-CH.61+878-YTS
Images
MNRUB128B-CH.59+607-YTS
Images
MNRUB-121-Ch.51+654-YTS
Images
Isolated Tunnel No work
Images
Isolated Deep cut WIP
Images
North tunnel south portal No work
Images
North tunnel north portal wip
Images
North deep cut Wip
Images
South tunnel south portal No work
Images
South tunnel North portal -WIP
Images
MJB-114 Kalyan
Images
MJB-136-CH.65+776.31-(A1)WSS
Images
MJB-136-CH.65+776.31-(A2)WSS
Images
MJB-106
Images
MJB-114.
Images
MJB-119B-Ch.50+300-YTS
Images
MJB134-CH.63+721-(A2)WSS
Images
MJB134-CH.63+721-S(A1)WSS
Images
MJB137-CH.67+951.49-(A1)
Images
MJB137-CH.67+951.49-(A2)WIP
Images
MJRUB127-CH.59+407.50-YTS
Images
Gawan phata ROB work stopped since 02.02.24
Images
1UPCO-CH.69+005-WIP
Images
Kharvao Viaduct-CH.68+885-WIP
Images
KHARVAOVIADUCT(A1)-CH.1+622-WSS
Images
P38-CH.1+622-WSS
Images
A2-Ch.51+247-WIP
Images
Span A1-P2-Ch.51+047-51+247-WSS
Images
Span P3-P7-Ch.51+047-51+247-WSS
Images
Span P8-P10-Ch.51+047-51+247-WIP
Images
Span P10-P12-Ch.51+047-51+247-WIP
Images
Span P12-P14-Ch.51+047-51+247-WIP
Images
Span P14-P15-Ch.51+047-51+247-WIP
Images
Span P17-A2-Ch.51+047-51+247-WIP
Images
MNB-121A-Ch.52-148-WSS
Images
MNB-121B-Ch.52+708-YTS
Images
MNB140-CH.70+304-YTS
Images
MNB137D-CH.67+244-WSS
Images
MNB140A-CH.70+495-WSS
Images
MNB137C-CH.66+870-YTS
Images
MNB137B-CH.66+612-WIP
Images
MNB137A-CH.66+410-WSS
Images
MNB134B-CH.64+318-WSS
Images
MNB134A-CH.64+162-WIP
Images
MNB133D-CH.62+607-WSS
Images
MNB133C-CH.62+507-WSS
Images
MNB132A-CH.61+594-YTS
Images
MNB129-CH.62+348-YTS
Images
MNB129-CH.60+523-WSS
Images
MNB128-CH.60+222-WIP
Images
MNB128C-CH.59+461-YTS
Images
MNB127D-CH.59+129-WSS
Images
MNB127C-CH.58+926-YTS
Images
MNB127B-CH.58+306-WIP
Images
MNB127A-CH.58+088-WIP
Images
MNB126B-CH.57+246-WSS
Images
MNB126A-CH.56+832-WIP
Images
MNB125D-CH.56+467-WIP
Images
MNB125-CH.56+682-WIP
Images
MNB125A-CH.55+955-WIP
Images
MNB124-CH.55+317-YTS
Images
MNB124A-CH.55+134-YTS
Images
MNB123A-CH.54+675-YTS
Images
MNB-121D-Ch.53+014-YTS
Images
MNB-121C-Ch.52+905-YTS
Images
MNB127C-CH.58+926-YTS (No further progress till date)
Images
MRUB-106A Rock breaking -WIP
Images
MNRUB123-CH.54+787-YTS
Images
MNRUB-121E-Ch.53+280-YTS
Images
MJB 136 – View from ROW – WSS
Images
2UPCO-CH.69+396-WSS
Images
MJB125B-CH.56+152-WSS
Images
MJB 134 – View from Vaitarna- ROW corner- WSS
Images
MJB138-CH.68+447.94-WSS
Images
MJB139-CH.69+396-WSS
Images
MJB 147 -WSS
Images
MJB 169A -WSS
Images
MJRUB 127 – View from JNPT-ROW End – YTS
Images
MJRUB 127 – View from VAITARNA-ROW End – YTS
Images
ROB Bhiwandi – View from JNPT End – WSS
Images
ROB Bhiwandi – View from Vaitarna End – WSS
Images
Bhiwandi Pipeline-CH.56+293-Completed
Images
6. JNPT Tower Wagon She’d- work not started
Images
5. JNPT Staff quarters Type 3-(YTS)
Images
4. JNPT Staff quarters Type 2 and Keymen- (YTS)
Images
3. JNPT Relay Hut- West (YTS)
Images
2. JNPT Relay hut East- (YTS)
Images
1. JNPT IMD Building- Work not started
Images
Kharbao Type 3 quarters- work not started
Images
Kharbao Tower Wagon Shed- Work yet to start
Images
Kharbao Relay hut West- work not started
Images
Kharbao Relay hut- East
Images
Kharbao IMD Building- Work not started
Images
Nilje quarters Type 3- work not started
Images
Nilje quarters Type 2- Work stopped since 18.06.2022
Images
Nilje MMU building- work not started
Images
Nilje Keymen- work stopped since 06.02.2022
Images
07.02.2024
Images
North Deep cut No work P-1
Images
05.02.2024
Images
02.02.2024
Images
MJRUB -67 work stand still since 27.01.24 ( backfilling work ).
Images
Kharbao Service Building- Work not started
Images
IG-17 girder shuttering work in progress. Kopar viaduct.
Images
WSS between ch 58+100 to ch 58+600
Images
WSS between ch 58+100 to ch 58+800
Images
WSS between ch 58+100 to ch 59+00
Images
WSS between ch 58+600 to ch 59+100
Images
WSS between ch 58+800 to 59+100
Images
WSS between ch 60+650 to ch 61+050
Images
WSS between ch 61+600 to ch 61+900
Images
WSS between ch 63+300 to ch 63+700
Images
WSS between ch 65+200 to ch 65+900
Images
WSS between ch 66+800 to ch 67+300
Images
WSS between ch 73+600 to ch 79+900
Images
WSS between ch 77+850 to ch 78+200
Images
WSS between ch 78+600 to ch 78+900
Images
WSS between ch 81+500 to ch 81+950
Images
WSS between ch 84+00 to ch 84+460
Images
WSS between ch 84+100 to 84+520
Images
WSS between ch 84+100 to ch 84+500
Images
WSS between ch 84+100 to ch 84+600
Images
WSS between ch 84+400 to. ch 84+760
Images
WSS between ch 84+500 ch 84+750
Images
WSS between ch 86+350 to ch 87+00
Images
WSS between ch 86+470 to ch 86+800
Images
WSS between ch 86+500 to ch 87+060
Images
WSS between ch 86+500 to ch 87+100
Images
WSS between ch 96+700 to 97+200
Images
WSS between ch 96+700 to ch 97+200
Images
WSS ch 73+200 to ch 73+800
Images
WSS ch 96+700 to ch 97+200
Images
Work in progress IR existing bridge dismantling and stone column completed
Images
Work yet to start from Ch19+520 to 19+700
Images
Work yet to start from Ch19+520 to 19+700
Images
Work yet to start from Ch19+520 to 19+700
Images
Work yet to start from Ch19+520 to 19+700 (2)
Images
Work yet to start from ch19+520 to 19+700.
Images
work not yet started between ch 58+600 to ch 59+050
Scroll to Top